/skill-estimation

AL project estimation for Business Central. Use when estimating development effort, creating cost models, SWOT analysis, or structuring project proposals.

BOOST
From plugin
aldc-al-development-collection
11237 skills28 agents11 commands4 MCP
Install
$ npx -y skills add javiarmesto/ALDC-AL-Development-Collection --skill skill-estimation --agent claude-code

How it fires

How this skill gets triggered: by you, by Claude, or both.

  • Fires itselfAuto-invocation. Claude auto-loads it when your prompt matches the work.Auto-invocation is when the right skill fires by itself at the right moment, driven by a FLOW.md router and a hook, instead of you invoking it by name. It is the difference between a skill being installed and a skill actually getting used.Read the full definition →
  • You can call itInvoke it directly when you want it.
  • Slash command/skill-estimation

Context preview

The summary Claude sees to decide when to auto-load this skill.

AL project estimation for Business Central. Use when estimating development effort, creating cost models, SWOT analysis, or structuring project proposals.

SKILL.md

skill-estimation.SKILL.md
name: skill-estimation
description: "AL project estimation for Business Central. Use when estimating development effort, creating cost models, SWOT analysis, or structuring project proposals."

Skill: AL Project Estimation

Purpose

Estimate AL/Business Central projects: complexity scoring, PERT 3-point estimation, SWOT/DAFO risk analysis, cost breakdown by phase, resource allocation, and structured presales documentation.

When to Load

This skill should be loaded when:

  • A new BC/AL project needs time and cost estimation
  • A feasibility assessment or SWOT analysis is required before commitment
  • A presales proposal or technical assessment document is being created
  • Resource allocation and team composition need to be defined
  • A project plan with milestones and payment schedule is needed

Core Patterns

Pattern 1: Intake Questions (Mandatory)

Before any estimation, gather these parameters:

## Project Intake — Required Information

### 1. Project Identity
- Project name (will be used for folder structure)
- Brief description: What problem does it solve?

### 2. Cost Parameters (MANDATORY)
- Hourly rate (e.g., €75/hour, $100/hour)
- Currency (EUR, USD, GBP)
- Contingency buffer: Yes/No (default 15-20%)
- Risk buffer: Low (10%), Medium (20%), High (30%)

### 3. Technical Context
- Target BC version: SaaS, On-Premise, or both?
- Target delivery date
- Existing codebase? (repository URL or workspace path)
- Reference repositories for similar functionality?

### 4. Team (optional)
- Available developers: Junior, Mid, Senior?
- BC experience level: New, Experienced, Expert?

**PAUSE — do NOT proceed without cost parameters. Estimation without rates is meaningless.**

Pattern 2: Complexity Scoring

Score each dimension 1-10 to derive overall project complexity:

## Complexity Assessment

| Dimension | Score (1-10) | Criteria |
|---|---|---|
| Data Model | /10 | Tables, relations, migration needs |
| Business Logic | /10 | Codeunits, validations, calculations |
| UI Complexity | /10 | Pages, customizations, RoleCenter |
| Integrations | /10 | External APIs, events, webhooks |
| Reporting | /10 | Reports, queries, analytics |
| Security | /10 | Permissions, data sensitivity, audit |
| Testing | /10 | Test coverage needed, edge cases |
| Migration/Upgrade | /10 | Data migration, version compatibility |

**Overall Complexity**: (sum / 80) × 10 = X/10

**Object count estimation:**

| Object Type | Low Complexity | Medium | High | |---|---|---|---| | Table | 2-4 hrs | 4-8 hrs | 8-16 hrs | | Page (Card/List) | 2-4 hrs | 4-8 hrs | 8-16 hrs | | Page (Document) | 4-8 hrs | 8-16 hrs | 16-32 hrs | | Codeunit | 2-8 hrs | 8-16 hrs | 16-40 hrs | | Report | 4-8 hrs | 8-16 hrs | 16-32 hrs | | Integration | 8-16 hrs | 16-32 hrs | 32-80 hrs |

Pattern 3: PERT 3-Point Estimation

Use the Program Evaluation and Review Technique for each task:

## PERT Formula

E = (O + 4M + P) / 6

Where:
- O = Optimistic (best case, everything goes right)
- M = Most Likely (normal case, typical obstacles)
- P = Pessimistic (worst case, major obstacles)
- E = Expected duration

Apply per development phase:

## Phase Breakdown

### Phase 1: Analysis & Design
| Task | O (hrs) | M (hrs) | P (hrs) | E (hrs) |
|---|---|---|---|---|
| Requirements analysis | 8 | 16 | 24 | 16 |
| Technical design | 8 | 12 | 20 | 13 |
| Architecture review | 4 | 8 | 12 | 8 |
| **Subtotal** | **20** | **36** | **56** | **37** |

### Phase 2: Development
| Task | O (hrs) | M (hrs) | P (hrs) | E (hrs) |
|---|---|---|---|---|
| Tables & data model | X | X | X | X |
| Pages & UI | X | X | X | X |
| Business logic | X | X | X | X |
| Integrations | X | X | X | X |
| **Subtotal** | **X** | **X** | **X** | **X** |

### Phase 3: Testing & QA
| Task | O (hrs) | M (hrs) | P (hrs) | E (hrs) |
|---|---|---|---|---|
| Unit tests | X | X | X | X |
| Integration tests | X | X | X | X |
| UAT support | X | X | X | X |
| Bug fixes | X | X | X | X |
| **Subtotal** | **X** | **X** | **X** | **X** |

### Phase 4: Deployment & Documentation
| Task | O (hrs) | M (hrs) | P (hrs) | E (hrs) |
|---|---|---|---|---|
| Technical documentation | X | X | X | X |
| Training materials | X | X | X | X |
| Deployment | X | X | X | X |
| Post-go-live support | X | X | X | X |
| **Subtotal** | **X** | **X** | **X** | **X** |

Pattern 4: SWOT/DAFO Analysis

Structured risk and opportunity assessment:

## SWOT Analysis

### Strengths (Internal Positive)
| ID | Strength | Impact |
|---|---|---|
| S1 | [e.g., Team has BC experience] | High/Medium/Low |

### Opportunities (External Positive)
| ID | Opportunity | Impact |
|---|---|---|
| O1 | [e.g., Standard BC API available] | High/Medium/Low |

### Weaknesses (Internal Negative)
| ID | Weakness | Impact | Mitigation |
|---|---|---|---|
| W1 | [e.g., No existing test suite] | High | Implement TDD from start |

### Threats (External Negative)
| ID | Threat | Probability | Impact | Mitigation |
|---|---|---|---|---|
| T1 | [e.g., BC version upgrade mid-project] | Medium | High | Pin BC version |

## Feasibility Score

| Criterion | Score (1-10) |
|---|---|
| Technical Feasibility | /10 |
| Resource Feasibility | /10 |
| Timeline Feasibility | /10 |
| Economic Feasibility | /10 |
| **Overall** | **/10** |

### Recommendation
- [ ] **GO** — Project viable, proceed
- [ ] **CAUTION** — Viable with conditions
- [ ] **NO-GO** — Not recommended currently

Pattern 5: Cost Summary and Payment Milestones

Consolidate estimation into a financial summary:

## Cost Summary

| Concept | Hours | Rate | Cost |
|---|---|---|---|
| Analysis & Design | X | [RATE] | [TOTAL] |
| Development | X | [RATE] | [TOTAL] |
| Testing & QA | X | [RATE] | [TOTAL] |
| Deployment & Docs | X | [RATE] | [TOTAL] |
| **Subtotal** | **X** | | **[TOTAL]** |
| Contingency ([%]%) | X | | [TOTAL] |
| Risk Buffer ([%]%) | X | | [TOTAL] |
| **TOTAL** | **X** | |